14.4.4 Details for connections between precast members and the foundation
SBC 312 · Edition 2024 · p. 190
These are the clause's opening lines. The full clause, with its tables and exceptions, opens in the code reader.
Read the full clauseUnder this clause
- 14.4.4.1 At the base of a precast column, pedestal, or wall, the connection to the foundation shall satisfy the requirements of (Section 14.3.4.3 or 14.3.5.2).
- 14.4.4.2 If the applicable load combinations given in (Section 14.4.3) do not result in any tension at the base of precast walls, it is permitted to consider the vertical structural integrity ties required in ((Section 14.3.4.3 (b) as a reinforced concrete slab bearing on the ground (slab-on-ground).