24.2.5 Calculation of Deflection Values for Composite Concrete Construction
SBC 311 · Edition 2024 · p. 129
These are the clause's opening lines. The full clause, with its tables and exceptions, opens in the code reader.
Read the full clauseUnder this clause
- 24.2.5.1 Where composite concrete flexural members are shored during construction, the dead load shall be resisted by the full composite section after removal of the temporary shoring. For the purpose of calculating deflection, the composite member is also permitted to be considered equivalent to a member cast as a single mass.
- 24.2.5.2 If composite concrete flexural members are not shored during construction, the magnitude and duration of load before and after composite action becomes effective shall be considered in calculating long-term deflection.
- 24.2.5.3 Deflection resulting from differential shrinkage of composite members, whether precast or cast-in-place, shall be taken into consideration.