13.2.8 Development of reinforcement in shallow foundations and pile caps
SBC 311 · Edition 2024 · p. 95
These are the clause's opening lines. The full clause, with its tables and exceptions, opens in the code reader.
Read the full clauseUnder this clause
- 13.2.8.1 Development of reinforcement shall conform to the requirements of CHAPTER 25.
- 13.2.8.2 The calculated tension or compression force in the reinforcement at each section shall be developed on each side of that section.
- 13.2.8.3 Critical sections for development of reinforcement shall be assumed at the same locations as indicated in (Section 13.2.7.1) for maximum factored moment, and at all other vertical planes where changes in section or reinforcement occur.
- 13.2.8.4 Adequate anchorage shall be provided for tension reinforcement where reinforcement stress is not directly proportional to moment, such as in sloped, stepped, or tapered foundations; or where tension reinforcement is not parallel to the compression face.