11.1.4 Prequalification Variables
SBC 307 · Edition 2024 · p. 107
In order for a connection to be prequalified, the effect of the variables listed in (Section 11.1.4) that influence the performance of the connection shall be taken into consideration. The Connection Prequalification Review Panel (CPRP) shall establish the permissible limits…
These are the clause's opening lines. The full clause, with its tables and exceptions, opens in the code reader.
Read the full clauseUnder this clause
- 11.1.4.1 Beam and column factors for SMF and IMF moment frame systems, and link and column factors for EBF
- 11.1.4.2 Beam and Column Factors for C-SMF and C-IMF moment frame systems
- 11.1.4.3 Beam-to-Column or Link-to-Column Connections
- 11.1.4.4 Continuity Plates and Side Plates
- 11.1.4.5 Welds
- 11.1.4.6 Bolts
- 11.1.4.7 Reinforcement in C-SMF and C-IMF Systems
- 11.1.4.8 Quality Control and Quality Assurance
- 11.1.4.9 Additional Connection Details