2.1.2.1 A site investigation report is not required to be prepared if the building satisfies all of the following common criteria:

SBC 303 · Edition 2024 · p. 22

1. The net loads applied to the foundation are less than 50 kPa. 2. The absence of dynamic loads or vibratory loads on the building. 3. The absence of questionable soil or problematic soil (expansive, collapsible, or sabkha) beneath the…

These are the clause's opening lines. The full clause, with its tables and exceptions, opens in the code reader.