- 14.4.1 Deep foundations shall be constructed in accordance with the requirements of (Section 14.4). Where a deep foundation element consists of two or more sections of different materials or different types spliced together, each section shall satisfy the construction requirements applicable to the element.
- 14.4.2 Structural Integrity
- 14.4.3 Material Identification
- 14.4.4 Location Plan
- 14.4.5 Predrilling
- 14.4.6 Vibratory Driving
- 14.4.7 Heaved Elements
- 14.4.8 Cast-in-Place Enlarged-Base Elements
- 14.4.9 Cast-in-Place Hollow-Stem Auger Elements
- 14.4.10 Drilled Cased Piles Extending into Rock
- 14.4.11 Micropiles
- 14.4.12 Helical Piles
- 14.4.13 Special Inspection