5.3.2.10 Complete re-shoring shall be provided when the original forms and shores are removed, where the concrete is required to support loads in excess of its capacity.
SBC 302 · Edition 2024 · p. 39
These are the clause's opening lines. The full clause, with its tables and exceptions, opens in the code reader.