10.1.4 Submittal submitted by the contractor
SBC 302 · Edition 2024 · p. 61
These are the clause's opening lines. The full clause, with its tables and exceptions, opens in the code reader.
Read the full clauseUnder this clause
- 10.1.4.1 Concrete mixture proportions shall be submitted by the contractor to the engineer/architect for review and approval.
- 10.1.4.2
- 10.1.4.3 The contractor shall submit procedures for the production, placement, finishing, and curing and protection of concrete during hot weather conditions to the engineer/architect for review and approval prior to the preplacement conference.
- 10.1.4.4 The submittals from the contractor shall indicate the methods to be used for the initial and final cooling of the concrete and the sequence in which they will be initiated where multiple methods are proposed.