8A2.2.2.2 Curing
SBC 1101 · Edition 2024 · p. 293
The finish coat of two-coat plaster shall not be applied until at least 48 hours after the application of the base coat. In three-coat plaster, the second coat shall not be applied until at least 24 hours after the application…
These are the clause's opening lines. The full clause, with its tables and exceptions, opens in the code reader.