712.1 General
SBC 1101 · Edition 2024 · p. 261
These are the clause's opening lines. The full clause, with its tables and exceptions, opens in the code reader.
Read the full clauseUnder this clause
- 712.1.1 Concrete slabs on ground shall be designed and constructed in accordance with the requirements of (Section 712).
- 712.1.2 Where foundation slabs are used to transmit loads from other portions of the structure to the supporting soil, their design shall comply with the requirements of the applicable provisions of (Chapter 7).
- 712.1.3 SBC 1101 does not cover the design of pavements or slabs on grade that are subject to concentrated loads.
- 712.1.4 All vegetative matter, topsoil, and foreign materials shall be removed from the site prior to construction of the foundation slab.
- 712.1.5 Backfill materials shall be free of vegetation and foreign matter. Backfill materials shall be compacted to ensure uniform support of the slab.
- 712.1.6 A layer of polyethylene or a vapor retarder with overlapping joints shall be placed between the concrete floor slab and the base course, or the subbase in the absence of a base course.